Remaining work and %work complete

P

Perl

Hello,

We have Project Server 2003.

One of my resources update actual work from PWA. and change remaining work
to 0 hours.
At % work complete column he gets 96%. why not 100% ?

BTW, I accept his update. At MSP I see that task is complete.

Any Idea ?

Perl
 
Top