M
Murthyu
I have a question related to updating tasks using PWA. My resources are
updating the Remaining work for their tasks, however, when updates are made,
PWA seems to change the work field also at the same time - and gives the work
field the same value as the remaining work that they just entered.
This is obviously causing a mess in my plan
Using Project 2003.
Interestingly, I have the field "% of work complete" checked in the
Customize Project Web Access/Tracking page under Admin. I had wanted to
ensure that everyone was tracking % of work complete instead of remaining
hours - but I guess that is a different problem
Can someone pls let me know what I am doing wrong?
updating the Remaining work for their tasks, however, when updates are made,
PWA seems to change the work field also at the same time - and gives the work
field the same value as the remaining work that they just entered.
This is obviously causing a mess in my plan
Using Project 2003.
Interestingly, I have the field "% of work complete" checked in the
Customize Project Web Access/Tracking page under Admin. I had wanted to
ensure that everyone was tracking % of work complete instead of remaining
hours - but I guess that is a different problem
Can someone pls let me know what I am doing wrong?