Hi smart people out there,
we encounter the following problem after migrating from Project Server 2002
to Project Server 2003 with managed time periods:
In several projects the remaining work disappears (becomes zero) after
accepting actuals.
Does anyone recognise this problem? Does anyone know how to solve this?
Regards,
Wouter
we encounter the following problem after migrating from Project Server 2002
to Project Server 2003 with managed time periods:
In several projects the remaining work disappears (becomes zero) after
accepting actuals.
Does anyone recognise this problem? Does anyone know how to solve this?
Regards,