Remaining Work not reflected in multi project Resource Usage

C

Charles

I have a resource tasked to multiple projects. If I open project A, usage
shows work=100 hrs and remaining work=50hr.

If i open project B and look at resource usage it shows Project A usage of
Work=100 hrs and remaining work=100hrs.

What gives?
 
D

Dale Howard [MVP]

Charles --

What happens if you open both Project A and Project B at the same time?
 
Top