Using Project Server 2002, Project Pro 2002, both SP1.
I have a task with 1 assignment.
The assignment/task work = 2000 hrs
The assignment/task actual work = 500 hrs
The assignmnet/task remaining work = 1500 hrs
But when I look at the remaining work on this assignment
in a Task Usage view, the sum of the remaining work (right
hand pane) = 3000 hrs !!! In a daily view instead of
seeing 8 hrs a day, I see 16 hrs.
Can anyone explain how this can happen?
Thanks
Stuart.