Hi Gary, sorry for taking so long.
I did some tests with the resource having the problem.
Republishing the assignment is now making the remaining
hours vary accordingly with what is in the project plan
BUT for some odd reason, this resource's timesheet is
always keeping an extra 10.5 hours of remaining hours (???)
This difference is only in the timesheet view, all other
project views (assignments details, resource work, ...)
are fine.
I suspect the initial tracking method used is kind of the
culprit (after reading a similar problem from Jerry Ewing -
"Remaining hours not updating" in this newsgroup).
Any suggestions on how I can get rid of these "ghost"
remaining hours?
Would saving the project to a file, deleting it from the
server, re-importing it back to the server and
republishing it resolve this ?
Thanks.
Ben
(PS. looking in the database, there is a 10.5 hours
difference (assignments vs web_assignments) in the actual
hours work. Is this the problem?)