This problem is occuring only with tasks that are assigned to material type
resources. The costs are updated monthly using the Task Usage view by our
Accounting Tech. For some reason the remaining work ($1=1 unit) is splitting
and extending out beyond the original end dates. No constraints or
dependencies. No "split tasks in progress". I'm baffled by this behavior.
Even when I pull the task back and zero out the remaining work, the next time
the project is "synced to actuals" and saved the task is again split and
pushed out. Sometimes several years.
resources. The costs are updated monthly using the Task Usage view by our
Accounting Tech. For some reason the remaining work ($1=1 unit) is splitting
and extending out beyond the original end dates. No constraints or
dependencies. No "split tasks in progress". I'm baffled by this behavior.
Even when I pull the task back and zero out the remaining work, the next time
the project is "synced to actuals" and saved the task is again split and
pushed out. Sometimes several years.