T
Tony
We are currently experiencing weird and unpredictable changes in
remaining work and task duration in several projects in our Project
Server database. It appears to be happening when synchronizing actuals
to protected actuals (the system is set up for managed time periods).
For example remaining work on an assignment changes from 75 to 45.5
hours after syncing, while no actuals on the affected task were out of
sync in the first place.
Does anyone:
1) experience similar behaviour
2) have an explanation
3) have a solution
Let's solve this people.... ;-)
remaining work and task duration in several projects in our Project
Server database. It appears to be happening when synchronizing actuals
to protected actuals (the system is set up for managed time periods).
For example remaining work on an assignment changes from 75 to 45.5
hours after syncing, while no actuals on the affected task were out of
sync in the first place.
Does anyone:
1) experience similar behaviour
2) have an explanation
3) have a solution
Let's solve this people.... ;-)