Hello
We have some tasks in the project schedule that are completed and there
is no more budget allocated for them. Is there a way of removing these
tasks from the resources timesheet so that they can't complete any time
against them without removing them from the project schedule?
I know that I can mark the resources as Proposed but that won't work as
they are still committed to other tasks in the project which are still
current.
Also, from my understanding they can click on the "Hide task" button on
their timesheet but as soon as the project is republished then they
reappear again.
I would really appreciate any help.
Thanks
Rosa
We have some tasks in the project schedule that are completed and there
is no more budget allocated for them. Is there a way of removing these
tasks from the resources timesheet so that they can't complete any time
against them without removing them from the project schedule?
I know that I can mark the resources as Proposed but that won't work as
they are still committed to other tasks in the project which are still
current.
Also, from my understanding they can click on the "Hide task" button on
their timesheet but as soon as the project is republished then they
reappear again.
I would really appreciate any help.
Thanks
Rosa