Removing deleted assignments from PWA

J

Jan M.

Hi,

Some assignments have been deleted from a project. They still appear in the
resource timesheet and in the view resource assignment page. In the view
resource assignment page, remaining work of those deleted assignments is
still included in the calculation of the summary remaining work.

Now, the resource has left the company and we cannot access his timesheet to
hide the task. The resource manager would like to see this resource
assignments in PWa in order to reassign new resource to those tasks.

How can I get rid of those deleted assignments in PWA?

Thanks,

Jan M.
 
M

Mauricio@BVFG

I have used the SQL file to remove deleted tasks and I wonder if there is a
middle ground solution.

I see on the Timesheet some out of the box filters among which the "Tasks
deleted by manager". Does anybody know how to reverse this filter?

Thanks

Mauricio
 