Removing resources from a project

K

Kate

Hi,

Does anyone know an easy way to stop a resource assigning
themselves to a task on a project? Once I have built them
onto the team and they have completed their tasks, I want
to prevent them booking any further time.

Thanks

Kate
 
G

Greg Horodeck

If they have no other work to perform on the project, change their booking
type to "Proposed". Nothe, this only work for Project 2003. All tasks for
the project will be removed from the resources time sheet.

Note, booking status is project wide, you cannot assign booking status for a
resource at the task level.


Greg
 