Rename Fields in PWA

D

David

Hello - i am sure this is a simple question - but i just
cant figure it out...

I have inserted some new text fields to the Task view in
Project - now i would like to have thouse fields displayed
in the task view in PWA, how do i do this???

additionally i have givem them new names, (Remaining Work
is calles ETC...) how can i make them appear in PWA and
also appear with the same names i defined...

Thanks for your help

regards

David
 
D

Dale Howard [MVP]

David --

Open the project in question and then click Tools - Customize - Published
Fields. Select the new fields from the list on the left and copy them to
the list on the right, and then click OK. Click Collaborate - Publish -
Republish Assignments and then click OK. This step will "push" the new
fields to the View my tasks page in PWA. If you are using Project Server
2003, however, your Project Server administrator will still need to modify
the Timesheet view to include the new fields in the order you wish them to
be displayed.

If your additional fields are standard fields (Remaining Work is a standard
field) then you cannot rename the fields in PWA. If they are custom fields,
then your Project Server administrator would need to rename them in the
Enterprise Global file using Tools - Customize - Enterprise fields. Hope
this helps.
 
Top