Hi,
If say a a prototype of a product has been created and shown to the customer
for feedback. The customer then wants some rework on the prototype. Once the
rework has been created, it will be shown again to the customer for feedback
until the customer is fully happy with the product. However there isn't
always rework as sometimes the customer is happy with the first prototype.
My question is, what is the best way for MS Project 2003 to take these tasks
into consideration? The tasks goes round in circles, but sometimes it doesn't.
Sorry I haven't explained it well, hope someone can give me help. Thanks alot!
WSH
If say a a prototype of a product has been created and shown to the customer
for feedback. The customer then wants some rework on the prototype. Once the
rework has been created, it will be shown again to the customer for feedback
until the customer is fully happy with the product. However there isn't
always rework as sometimes the customer is happy with the first prototype.
My question is, what is the best way for MS Project 2003 to take these tasks
into consideration? The tasks goes round in circles, but sometimes it doesn't.
Sorry I haven't explained it well, hope someone can give me help. Thanks alot!