K
ks2008
Hi
Please review the question. This is from
MCTS Self-Paced Training Kit: Managing Projects with Microsoft Office
Project 2007 (Exam 70-632)"
Chapter 2, Lesson 4.
My Question is, why Answer B is not correct.
I could able to replace the assigned resource using Task Information dialog
box’s Resources tab.
Question
=========
Due to an unexpected change in scope by your stakeholders, you need to
change the resources applied to the task of finishing the interior of a new
conference room. The two resources currently applied to this task are
Wallpaper Hanger and Carpet Contractor. Your stakeholders have decided that
although they still want to finish the conference room, they want to lay tile
and paint the walls instead. The cost for laying tile is about the same as
laying carpet; the cost for painting the walls is about the same as hanging
wallpaper. You have created two new resources: Tile Contractor and Painter.
What do you do now?
A)In the Assign Resources dialog box for the task of finishing the interior
of the conference room, select the two existing resources (Wallpaper Hanger
and Carpet Contractor) and replace them with the new resources (Tile
Contractor and Painter).
B)In the Task Information dialog box’s Resources tab for the task of
finishing the interior of the conference room, select the two existing
resources (Wallpaper Hanger and Carpet Contractor) and replace them with the
new resources (Tile Contractor and Painter).
C)In the Resource Information dialog box’s General tab for the two existing
resources (Wallpaper Hanger and Carpet Contractor), click Replace to replace
the old resources with the new resources (Tile Contractor and Painter).
D)From the View Bar, select Assign Resources. In the Assign Resources dialog
box for the task of finishing the interior of the conference room, select the
two existing resources (Wallpaper Hanger and Carpet Contractor) and replace
them with the new resources (Tile Contractor and Painter).
Correct Answer: A
A)Correct: To replace one resource with another, select the task and open
the Assign Resources dialog box.
B)Incorrect: The only place where you can replace one resource with
another is the Assign Resources dialog box. It is not an option in the Task
Information dialog box.
C)Incorrect: The only place where you can replace one resource with
another is the Assign Resources dialog box. It is not an option in the
Resource Information dialog box.
D)Incorrect: Although you do make this change in the Assign Resources
dialog box, there is no option to access it from the View Bar.
Please review the question. This is from
MCTS Self-Paced Training Kit: Managing Projects with Microsoft Office
Project 2007 (Exam 70-632)"
Chapter 2, Lesson 4.
My Question is, why Answer B is not correct.
I could able to replace the assigned resource using Task Information dialog
box’s Resources tab.
Question
=========
Due to an unexpected change in scope by your stakeholders, you need to
change the resources applied to the task of finishing the interior of a new
conference room. The two resources currently applied to this task are
Wallpaper Hanger and Carpet Contractor. Your stakeholders have decided that
although they still want to finish the conference room, they want to lay tile
and paint the walls instead. The cost for laying tile is about the same as
laying carpet; the cost for painting the walls is about the same as hanging
wallpaper. You have created two new resources: Tile Contractor and Painter.
What do you do now?
A)In the Assign Resources dialog box for the task of finishing the interior
of the conference room, select the two existing resources (Wallpaper Hanger
and Carpet Contractor) and replace them with the new resources (Tile
Contractor and Painter).
B)In the Task Information dialog box’s Resources tab for the task of
finishing the interior of the conference room, select the two existing
resources (Wallpaper Hanger and Carpet Contractor) and replace them with the
new resources (Tile Contractor and Painter).
C)In the Resource Information dialog box’s General tab for the two existing
resources (Wallpaper Hanger and Carpet Contractor), click Replace to replace
the old resources with the new resources (Tile Contractor and Painter).
D)From the View Bar, select Assign Resources. In the Assign Resources dialog
box for the task of finishing the interior of the conference room, select the
two existing resources (Wallpaper Hanger and Carpet Contractor) and replace
them with the new resources (Tile Contractor and Painter).
Correct Answer: A
A)Correct: To replace one resource with another, select the task and open
the Assign Resources dialog box.
B)Incorrect: The only place where you can replace one resource with
another is the Assign Resources dialog box. It is not an option in the Task
Information dialog box.
C)Incorrect: The only place where you can replace one resource with
another is the Assign Resources dialog box. It is not an option in the
Resource Information dialog box.
D)Incorrect: Although you do make this change in the Assign Resources
dialog box, there is no option to access it from the View Bar.