reporets non-project time

P

Paul

Hi folks,

is there a way to create reports over all resources
on "non-project time" that you find in the time-sheet?

Grtz, Paul
 
J

Jonathan

Yes, you can. But you got to do some dirty work. You have to dig into PS
database and pull out those info.
 