Report Estimated times - versus made real Hours

C

Cecilio

Somebody knows how i can do it?
can i get the predicted date aim - versus date real conclusion?

Thanks
 
R

Rod Gill

Yep. Save a Baseline via Tools, Tracking, Save Baseline before you track
progress then you can compare baseline work against Actual. Select View,
Table, Work to see work variance. There is also cost and finish variance
etc.
 
C

Cecilio

Thanks Rod

Rod Gill said:
Yep. Save a Baseline via Tools, Tracking, Save Baseline before you track
progress then you can compare baseline work against Actual. Select View,
Table, Work to see work variance. There is also cost and finish variance
etc.

--

Rod Gill
Project MVP
Visit www.msproject-systems.com for Project Companion Tools and more
 