S
ScS
Question: Is there a way in Project Server 2007 to create a report or view
that would indicate the date an individual resources updated their assigned
tasks via PWA?
Background.
I am new to Project Server 2007 (and to this discussion group for that
matter). I have created a view for each team member to update Actual Start
Date, Actual Work and Remaining work. I need the team leads to be able to
look at a report or view by user, the task(s) and last update date via pwa
for that task.
Thanks in advance.
that would indicate the date an individual resources updated their assigned
tasks via PWA?
Background.
I am new to Project Server 2007 (and to this discussion group for that
matter). I have created a view for each team member to update Actual Start
Date, Actual Work and Remaining work. I need the team leads to be able to
look at a report or view by user, the task(s) and last update date via pwa
for that task.
Thanks in advance.