Report indicating the last date a resource updated tasks via PWA

S

ScS

Question: Is there a way in Project Server 2007 to create a report or view
that would indicate the date an individual resources updated their assigned
tasks via PWA?

Background.

I am new to Project Server 2007 (and to this discussion group for that
matter). I have created a view for each team member to update Actual Start
Date, Actual Work and Remaining work. I need the team leads to be able to
look at a report or view by user, the task(s) and last update date via pwa
for that task.

Thanks in advance.
 
N

NZ Projects

Is your requirement specifically to identify the last date an assignment was
updated, or it is to identify those assignments which are falling behind
schedule ?

I'm not aware of how to implement the former. There is a [last update]
attribute, but only at the Project level.

The later can easily be achieved by viewing the [finish variance] for those
tasks finishing after the [baseline finish] date. Alternatively you could
find tasks that are < 100% complete and whose end date is < status date.
 