Does anybody know of a way to produce a report showing the non working time for all resources?
As my resources book vacation I show those dates as non working time on their calendar, I would like to then run a report which simply shows all resources and their non working time.
I know I can do it on a resource by resource basis in the Gantt view (right click in Gannt sheet-->non working time-->choose resource name) but I would like to be able do it for all resources in one reoport .
Any help would be appreciated
Regards
Tony
As my resources book vacation I show those dates as non working time on their calendar, I would like to then run a report which simply shows all resources and their non working time.
I know I can do it on a resource by resource basis in the Gantt view (right click in Gannt sheet-->non working time-->choose resource name) but I would like to be able do it for all resources in one reoport .
Any help would be appreciated
Regards
Tony