Report showing non working time

T

Tony S

Does anybody know of a way to produce a report showing the non working time for all resources?

As my resources book vacation I show those dates as non working time on their calendar, I would like to then run a report which simply shows all resources and their non working time.

I know I can do it on a resource by resource basis in the Gantt view (right click in Gannt sheet-->non working time-->choose resource name) but I would like to be able do it for all resources in one reoport .

Any help would be appreciated

Regards

Tony
 
L

Lon Swain

Tony,

I did something similar using MS Access to get to the
Project Data. Depending on your comfort level with Access
you can create any number of useful reports and data
access pages. If this is something you are comfortable
doing, send me an email at [email protected] and I can
give you enough information to get you started.

Lon
-----Original Message-----
Does anybody know of a way to produce a report showing
the non working time for all resources?
As my resources book vacation I show those dates as non
working time on their calendar, I would like to then run a
report which simply shows all resources and their non
working time.
I know I can do it on a resource by resource basis in the
Gantt view (right click in Gannt sheet-->non working time--
choose resource name) but I would like to be able do it
for all resources in one reoport .
 
Top