Reporting actuals in days/week in PWA

B

Beth

My client would like to be able to have their team members report their
actuals in the timesheet with days/week instead of hours/week. I cannot find
a way to change from hours to days. Any suggestions? Also, the same issue
is seen in the Adjust Actuals page (Resource Center) in which I cannot change
from hours/day to days/week. Thanks.
 
D

Dale Howard [MVP]

Beth --

Team members can enter Actual Work measured in days by entering a number
plus the "d" character, such as "1d". When they do so, the system will
convert the number to the correct number of hours. Otherwise, there is no
way to force the system to work the way your client wants. Hope this helps.
 
Top