Reporting on all projects?

B

Bill D

My company is fairly new to project. We have multiple
active projects (about 60)in our enterprise server. I
need to create a report that has:
milestones for each project, start/end date, actual start
and end date accross all of the projects. I am able to
do it for a single project by creating a table and report,
but I cannot figure out a way to display the same data on
everything in our enterprise pool
Is there a way?
 
A

Andrea Padovano

There are several ways.

It depends on what Project you are using.

I suppose 2002 or 2003 Project Server with Project Professional.

First you could use the View functionality in project web acces, by wich you
are able to extract information from projects.

Another way is to use a reporting tool, extracting data from SQL Server and
collecting information directly on db structure. DB documentation on Project
CD.

Hope this help.
 