Reporting on tasks-assignment

  • Thread starter Jan Paul Hoogendijk
  • Start date
J

Jan Paul Hoogendijk

Hi all,

i'm trying to set up a report with the portfolio analyzer
to report on "standard" tasks in several (20) projects. I
added a enterprise codeline on tasks but they won't apear
in the Pivot Field List. Obviously i'm doing sth wrong. (I
did rebuild the OLAP Cube)

I hope someone can tell me how to do it.

Thanks
 
G

Gary L. Chefetz

Jan Paul:

You're doing everything right, unfortunately, task level outline codes do
not get published to the cube. Only Enterprise Resource and Project Outline
codes get extended to the cube.


--
Gary Chefetz [MVP]
http://www.msprojectexperts.com
"We wrote the book on Project Server"

*** Remember to look for line breaks in links posted to the news group, use
cut and paste for these.
 