Reporting remaining work and % complete both

A

ann

Hi,

Is there a way that I can get team members to post remaining work as
well as % complete in the tasks view? The reporting option on the
server has been set to 'Actual work done and work remaining: Resources
report the actual work done and the work remaining to be done on each
task.'

Thanks,
Ann
 
D

Dale Howard [MVP]

Ann --

If your default method of tracking progress in Project Server is Actual work
done and work remaining, then team members cannot enter a % Work Complete
value. The only fields unlocked for editing in the View my tasks page are
the Actual Work and Remaining Work fields. If you need for team members to
enter % Work Complete and Remaining Work, then perhaps your organization
needs to change to the % Work Complete method of tracking progress in
Project Server. Using the % Work Complete method of tracking, the % Work
Complete and Remaining Work fields would be unlocked for editing. Hope this
helps.
 
D

Dale Howard [MVP]

Ann --

Project Server does not allow team members to enter a % Complete value.
Sorry.
 