Reporting

K

karens

I have a master project with approximately 30 subprojects. Each project has
a project manager. I want to be able to run a report that shows the project
managers and the activities that fall under that project manager within a
certain timeframe. Ultimately, I'd also like to be able to have a graph or
chart that shows how much % of work the PM has during a time frame. I'm
fairly new to Project, used to use Primavera. Can anyone help??
My report would look something like this:

Week 1 Week 2 Week 3
Week 4
Project manager task
task
task

Project Manager
Project Manager
 
R

Rob Schneider

I think all you have to do is display all the subprojects in that Master
Project, then use a filter (on the field(s) you wish to define as dates
for the filter) to limit the tasks. This would be shown in a Gantt
chart with Weeks as the time interval.


--rms

www.rmschneider.com
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top