Reports about resource usage among multiple projects

B

Bilal

hil all

We have configured and run our EPM solution based on Ms project 2007 and
Microsoft Project Professional 2007, now a new requirement I received from my
top management asking about a the following
- A report that can show the resource usage among multiple projects running
in parallel??
is it doable and how can I develop such a report

--

Best Regards

Bilal Okour
blog : http://ebilal.spaces.live.com
 
D

Dale Howard [MVP]

Bilal --

You should create a Data Analysis view for this purpose, based on the
MSP_Portfolio_Analyzer cube, for example. You can add the Resources and
Projects dimensions to the Row Fields drop area, the Time dimension in the
Column Fields drop area, and the one or more Total Fields in the Total
Fields drop area (such as Work, Actual Work, Cost, Actual Cost, etc.). Hope
this helps.
 