J
John
I am attempting to use the cost report in Project 2002 Professional. I
notice though that when I click on the views menu, then go to resource
sheet, then view and select the cost table, I am getting a cost view of the
resources assigned to this project across all projects that the resources
are assigned to. Similiarly, I can manage to get a list of all tasks the
resource is assigned to across all projects. Further, when I go to reports
and get a report of who does what, the report shows the assignments of the
resource across all projects.
I do not want this. I only want to see the costs of the resources for this
project only (like the view in PWA). Am I doing something wrong, or am I
misunderstanding the uses for these views/reports? Would someone help me
out please?
Thanks
John
notice though that when I click on the views menu, then go to resource
sheet, then view and select the cost table, I am getting a cost view of the
resources assigned to this project across all projects that the resources
are assigned to. Similiarly, I can manage to get a list of all tasks the
resource is assigned to across all projects. Further, when I go to reports
and get a report of who does what, the report shows the assignments of the
resource across all projects.
I do not want this. I only want to see the costs of the resources for this
project only (like the view in PWA). Am I doing something wrong, or am I
misunderstanding the uses for these views/reports? Would someone help me
out please?
Thanks
John