Vivek S --
If some of the tasks have multiple resources assigned to them, then the
easiest way to accomplish this is to do the following:
1. Open the project in question
2. Click View - Resource Usage
3. Locate the resource and then select only those assignments you wish to
publish for that resource
4. Click Collaborate - Publish - Republish Assignments
5. In the Republish Assignments dialog, make sure Selected Items is
selected at the top of the dialog
6. Click OK
Hope this helps.
--
Dale A. Howard [MVP]
Enterprise Project Trainer/Consultant
Denver, Colorado
http://www.msprojectexperts.com
"We wrote the books on Project Server"