Republishing timephase data

J

jb

All

I have modified a project plan saved it locaaly. I deleted
the old project plan, brought the new one back to the
server, publish all information. The project schedule
looks good, however the actual work in the project
schedule is not getting published to resources timesheets.
It says the total actual work but does not plop the hrs
for each day. Can anyone tell me I republish the ours on
those days to the resources timesheets?
thx
jb
 
D

Dale Howard

jb --

Open the project, then click Collaborate - Publish - Republish Assignments.
In the dialog box, select the "Overwrite actual work entered by resources"
option then click OK. This should take care of your problem.
 
J

jb

Thank you Dale!
-----Original Message-----
jb --

Open the project, then click Collaborate - Publish - Republish Assignments.
In the dialog box, select the "Overwrite actual work entered by resources"
option then click OK. This should take care of your problem.







.
 