H
Haixiang
I am updating a schedule (input progress info. actual start, % complete ...),
some tasks were delayed. i'm trying to reschedule them to start on Status
Date, and all tasks move accordingly as driven by dependency, it can give me
a forcast of how the whole project will be.
So I use "Tools">"Tracking">"update project">"Reschedule uncompleted work
to start after:"
After reschedule constraints (start no earlier than) were added to all tasks
except those actually started. I don't like these contrains,it make me
difficult to tell which constraint is added myself,and which is by the
rescheduling. Can it work as Primavera, or just add constraints to those must
have constraints, for example, task A will be rescheduled to start on 1st
March, so constraints must be added to make it start no earlier than 1st
March, but all successors of task A do not need constraints, there start
dates are driven by links.
Anyway I can choose to reschedule selected tasks,but to select these tasks
that must have constraints is not easy.
Is there any better solution?
thanks in advance.
some tasks were delayed. i'm trying to reschedule them to start on Status
Date, and all tasks move accordingly as driven by dependency, it can give me
a forcast of how the whole project will be.
So I use "Tools">"Tracking">"update project">"Reschedule uncompleted work
to start after:"
After reschedule constraints (start no earlier than) were added to all tasks
except those actually started. I don't like these contrains,it make me
difficult to tell which constraint is added myself,and which is by the
rescheduling. Can it work as Primavera, or just add constraints to those must
have constraints, for example, task A will be rescheduled to start on 1st
March, so constraints must be added to make it start no earlier than 1st
March, but all successors of task A do not need constraints, there start
dates are driven by links.
Anyway I can choose to reschedule selected tasks,but to select these tasks
that must have constraints is not easy.
Is there any better solution?
thanks in advance.