rescheduling of actual work

M

Miriam

Hi!

I have a project, published to project server where resources enter
their actual work (hours per day) via PWA.

Later I changed the nonworking time (holidays and sick time) in the
resources calendar of the resource global.

and now a strange effect occured:
Project has rescheduled the actual work entered by the resources in a
manner, that can not esaily be understood.

I did not expect actual work, that has been done on a certain day and
was entered from the resource in hours on this certain day, would be
rescheduled from project.

How is it possible that it happens?
How can I make this unwanted rescheduling undone?

thanks for help!
Miriam
 
D

dwolf

Have you tried Tools => Tracking => Sync to Protected Actuals in Pro?
This function is supposed to change all charges to match what has been
processed through the PWA timesheet. You can preview the differences
by adding a column to the Task Usage sheet for Actual Work Protected
and compare that with Actual Work.

Good luck and let us know how/if it works.

DWolf
 
M

Miriam

Thanks a lot.
Till now I haven't known that something like Protected Actuals existed
in Project.

With this synchrinization I could make all the unexpected and unwanted
changes undone.
And so my project plan with in the mean time 7.000 h of actual work is
correct again.

thank you,
Miriam
 