A
Alex
Has anyone attempted to spread a resource by percent
across a task and let project determine the date range?
For example:
I have a resource available for 3 hours per day. I set
his available time to 8:00 - 11:00 AM. Then I assign him a
9 hour task, but Project shows a start/end date of one day.
I tried leaving the available time alone and making the
resource available for 30%, but no difference.
-Alex
Reply with questions if I am not communicating effectively.
across a task and let project determine the date range?
For example:
I have a resource available for 3 hours per day. I set
his available time to 8:00 - 11:00 AM. Then I assign him a
9 hour task, but Project shows a start/end date of one day.
I tried leaving the available time alone and making the
resource available for 30%, but no difference.
-Alex
Reply with questions if I am not communicating effectively.