Resource Allocation in a Master Project Plan

G

Gretchen

I am trying to set up a master schedule for all of my company's
projects, with a special focus on providing a calendar or schedule which
shows who is working on what and when. I've assigned resources but when
I go to view Resource Usage, it goes by project but I can't tell which
project we're talking about. And because we try to make the task wording
consistent, it's very confusing.

What I would like (if it's possible) is to see one person's name and
below it, all of their tasks for all of the projects -- and the tasks
tagged in a way that I know which project that task goes with.

Is this even possible? (Please say yes!)
How to other folks use master project plans to easily track who is
doing what/when?

thanks!
 
M

Mike Glen

Hi Gretchen,

Welcome to this Microsoft Project newsgroup :)

In the Resource Usage view, try inserting the Project column.

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for my free Project Tutorials
 
J

JulieS

Hello Gretchen,

Add the Project field to the Resource Usage view. (Insert >Column
in the menu). The Project field will show the project name and path
that the assignments come from.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project
 
G

Gretchen

Ugh. You guys are brilliant! Now I'm embarrassed to say how long I've
been trying to figure this out THANK YOU!
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top