L
liati
Hello,
I don't know how to make this thing:
I'm working with the standard calendar (40 hours per week).
I have a work resource, named Liat, that have a limit of 10 hours per week,
so in the resource sheet I gave this worker Max Units of 0.25
I have another work resource, named Gidi, that can work the whole 40 hours
of the week, so I gave this worker Max Units of 1
Now there is a task, named A, with a duration of 5 hours. This task A needs
Gidi for the whole 5 hours, and needs Liat only for 3 hours.
how should I do it?
I tried to give resources to task A: I gave 1 unit of Gidi, and 0.6 units of
liat (needed 3 hours for a 5 hours task), but it looks like it is wrong..
what should I do?
thank's!
I don't know how to make this thing:
I'm working with the standard calendar (40 hours per week).
I have a work resource, named Liat, that have a limit of 10 hours per week,
so in the resource sheet I gave this worker Max Units of 0.25
I have another work resource, named Gidi, that can work the whole 40 hours
of the week, so I gave this worker Max Units of 1
Now there is a task, named A, with a duration of 5 hours. This task A needs
Gidi for the whole 5 hours, and needs Liat only for 3 hours.
how should I do it?
I tried to give resources to task A: I gave 1 unit of Gidi, and 0.6 units of
liat (needed 3 hours for a 5 hours task), but it looks like it is wrong..
what should I do?
thank's!