resource allocation view

J

jackie

Hello

Can you edit assignments in the graph in the resource allocation view in
order to remove overallocation or is there a better place in MS Project to do
this?

Many thanks
J
 
R

Rod Gill

Start by adjusting the logic of your links where possible then fine tune in
the Resource usage View by directly editing hours per week.

--

Rod Gill
Microsoft MVP for Project

Author of the only book on Project VBA, see:
http://www.projectvbabook.com
 