Resource Assignment View Gantt Progress Not Displayed

G

Gary Zag

Is there a way to configure the gantt chart in the Resource Assignment view
to show task progress the way that it is shown in a Project Details view?

Gary
 
G

Gary Zag

I figured it out. I did not have the % Work Complete field in my custom
view. Added the field and al is good.

Gary
 
Top