Good Afternoon
A problem was recently brought to my attention regarding the resource assignment view in PWA
When a PM or I go into Resources/view resource assignments and then select a given resource and click apply, no tasks appear in the xml grid even though we know there are tasks assigned both for current and all assignments
If we remove that resource, add a resoruce that we know works, click apply, then add the first resource back and apply, that resource's tasks appear
Does any one have any ideas as to why this is happening and/or have heard of a fix
Thanks for your help
Ryan
A problem was recently brought to my attention regarding the resource assignment view in PWA
When a PM or I go into Resources/view resource assignments and then select a given resource and click apply, no tasks appear in the xml grid even though we know there are tasks assigned both for current and all assignments
If we remove that resource, add a resoruce that we know works, click apply, then add the first resource back and apply, that resource's tasks appear
Does any one have any ideas as to why this is happening and/or have heard of a fix
Thanks for your help
Ryan