R
Rm
Hi,
I have a task with 3 resources attached. (Scheduled 01-Dec to 31-Dec)
One of the resources R1 started early on 15-Jun.
Another resource R2 started on 02-Dec.
Because of this a delay was added to the second resource, and the duration
was increased. Is it possible to prevent this? (Task Type is Fixed Duration
/ Effort Driven)
Also it is not possible to enter an actual finish date for R2?
Thanks,
I have a task with 3 resources attached. (Scheduled 01-Dec to 31-Dec)
One of the resources R1 started early on 15-Jun.
Another resource R2 started on 02-Dec.
Because of this a delay was added to the second resource, and the duration
was increased. Is it possible to prevent this? (Task Type is Fixed Duration
/ Effort Driven)
Also it is not possible to enter an actual finish date for R2?
Thanks,