Resource Assignments now showing up in Portfolio Analyzer

H

Hadi

this is driving me crazy. I have about 200 project schedules published on the
Server (2003). All of them use resources from the Enterprise pool. All of the
projcts and their resource assignments (hours $$) show up in OLAP cube in
Portfoio Analyzer except two projects. I can see them but not their
assignemtns. I see 0 work hours under these two projects. I've tried
rebuilding, starting fresh with new files, reassigning resource... but no
luck.

any ideas?

thank you

Hadi
 
H

Hadi

Gary..never mind i found the problem. it was an operating error on my part.
the assignments were out in 2013 and my Time filter in PWA stopped at 2011.
thanks for the reply anyways

Hadi
 