Resource Availability Best Practice

H

HZ

Is it wise to use the Resource Availability table to specify DAY BY DAY the
resources availability (say for a period of 1 year)?

I'm not sure if this will lead to some performance or unknown issues

Hope to hear an answer from one of the MVP folks

Thanks,
HZ
 
M

Mike Glen

Hi HZ,

Welcome to this Microsoft Project newsgroup :)

I'm not sure about wisdom, but it is much more easier and more controllable
through the resource's calendar. Tools/Change Working Time... /select the
resource and make all changes to the resources working time there.

FAQs, companion products and other useful Project information can be seen at
this web address: <http://www.mvps.org/project/>

Hope this helps - please let us know how you get on :))

Mike Glen
MS Project MVP
 