Resource Availability in PWA

N

Newbie

Hi,

In the "Assignments by project" view of the Resource Availability page in
PWA, the colored stacks of work by project are well displayed, but the brown
line of the resource total availability drops to zero on June 15th 2006.
All the resources are using the Standard calendar with availability until
20049.
What could be the reason for that?

Thanks for any idea!
 
D

Dale Howard [MVP]

Newbie --

The settings set by your Project Server administrator probably show resource
availability until June 14, 2006. After that it drops to 0. These settings
can be found in PWA by clicking Admin - Manage enterise features and setting
the "Date range for resource availability" options. Hope this helps.
 
Top