Hi all,
when I analyze resource assigments in the Resource Center,
I see that resources are available only for a few weeks. I
have published ressource information from several projects
at least 50 times. I've checked the calendars and
availability data several times. There are no changes in
the resource availability in the Resource Center.
What do I have to do to publish the availability in the
right way? (By the way, the assignments are published
correctly.)
Thanks,
Reiner