Steve Scott
I have a task that requires 10 days of Business Analyst (BA) resource in
October. How do I respresent the BA pool capacity for October if I know the
pool can only provide a maximum of eg 15 days work in October. The aim of
this is to then to be able to see that the BA resource is underallocated for
October. If I add another task that requires eg 6 days of BA resource in
October then I would expect to see the BA resource overallocated.
Any ideas??
Rgds
Steve
October. How do I respresent the BA pool capacity for October if I know the
pool can only provide a maximum of eg 15 days work in October. The aim of
this is to then to be able to see that the BA resource is underallocated for
October. If I add another task that requires eg 6 days of BA resource in
October then I would expect to see the BA resource overallocated.
Any ideas??
Rgds