T
Tartaglia
I have set several resources Available To values on the Resource
Information:Resource Availability grid to reflect a contract resource's
contract end date.
When I show the Columns for Available From and Available To on the Resource
Sheet view, if the Available To date I had set has past, the Available From
column shows the Available To date + 1 day @ 12:00 AM and nothing is shown in
the Available To column.
Can someone explain this behavior? If the Availabe To date I had set has
not past the columns show the correct information.
Specific Example:
For Resource A:
On Resource Information: Resource Availability grid, the first row has the
following values - Available From=NA, Available To=1/14/05, Units=1
When Displaying the Fields Availabile From and Available To on teh Resource
Sheet view I see the following values for Resource A:
Available From=1/15/05 12:00 AM
Available To=NA
I am running MS Office Proj Pro 2003 SP-1
Please Help me
David Coggan
Project Manager
(e-mail address removed)
Information:Resource Availability grid to reflect a contract resource's
contract end date.
When I show the Columns for Available From and Available To on the Resource
Sheet view, if the Available To date I had set has past, the Available From
column shows the Available To date + 1 day @ 12:00 AM and nothing is shown in
the Available To column.
Can someone explain this behavior? If the Availabe To date I had set has
not past the columns show the correct information.
Specific Example:
For Resource A:
On Resource Information: Resource Availability grid, the first row has the
following values - Available From=NA, Available To=1/14/05, Units=1
When Displaying the Fields Availabile From and Available To on teh Resource
Sheet view I see the following values for Resource A:
Available From=1/15/05 12:00 AM
Available To=NA
I am running MS Office Proj Pro 2003 SP-1
Please Help me
David Coggan
Project Manager
(e-mail address removed)