J
John
I have attached a calendar to several enterprise resources. The calendar
contains normal days off , plus our holidays (such as, Jan 1 and Jan 2 of
2004). However, after I build an OLAP cube (actually I just use the update
resource availibility option) with the dates set ahead for 6 months, I come
across something interesting. Project Pro 2002 (under the Build Team
option) shows the days as off, while PWA shows Jan 1 as off by not Jan 2.
This is also on several other days throughout the 2004 year
Can someone explain to me the reason for this discrepancy?
Thanks
John
contains normal days off , plus our holidays (such as, Jan 1 and Jan 2 of
2004). However, after I build an OLAP cube (actually I just use the update
resource availibility option) with the dates set ahead for 6 months, I come
across something interesting. Project Pro 2002 (under the Build Team
option) shows the days as off, while PWA shows Jan 1 as off by not Jan 2.
This is also on several other days throughout the 2004 year
Can someone explain to me the reason for this discrepancy?
Thanks
John