Resource Availibility Graph

J

John

I have attached a calendar to several enterprise resources. The calendar
contains normal days off , plus our holidays (such as, Jan 1 and Jan 2 of
2004). However, after I build an OLAP cube (actually I just use the update
resource availibility option) with the dates set ahead for 6 months, I come
across something interesting. Project Pro 2002 (under the Build Team
option) shows the days as off, while PWA shows Jan 1 as off by not Jan 2.
This is also on several other days throughout the 2004 year

Can someone explain to me the reason for this discrepancy?

Thanks
John
 
G

Gary L. Chefetz [MVP]

John:

Did you create a local calendar or Enterprise calendar. The former will not
populate to Project Web Access.
 
J

John

They are all enterprise calendars.

I assume that the resource availibility option button (in the OLAP build
admin section) is what populates Project Web Access?? (Would you confirm
this, please?) Is so, then I might have a quasi-answer. My OLAP cube quit
building as of December 4. I get no error messages - it just quit building
as of that date. My guess is that this has something to do with it. (Would
you confirm that as well?)


Thanks
John
 
Top