A
Andrew
Hi All,
I have a question in regards to Calendars used within
Project Server.
I have build 3 enterprise resource calendars and assigned
them to the resources with in the resource pool. Now in my
company they want to assign different calendars to
contractors and Permanent staff because they both work
different hours a week.
The question I have is when you build the project plan,
which calendar takes priority?
If I build a project plan and set the project plan to 8
hours of work a day then assign a resource whom only work
7.35hrs a day is there a way to adjust this task to make
this 7.35hr day 1 day for this task, with out adjusting
the percentage of effort for this resource.
Is there a way to use different resource calendars in
project plans that have different hrs per day with out
having to adjust %effort per task??
Andrew
I have a question in regards to Calendars used within
Project Server.
I have build 3 enterprise resource calendars and assigned
them to the resources with in the resource pool. Now in my
company they want to assign different calendars to
contractors and Permanent staff because they both work
different hours a week.
The question I have is when you build the project plan,
which calendar takes priority?
If I build a project plan and set the project plan to 8
hours of work a day then assign a resource whom only work
7.35hrs a day is there a way to adjust this task to make
this 7.35hr day 1 day for this task, with out adjusting
the percentage of effort for this resource.
Is there a way to use different resource calendars in
project plans that have different hrs per day with out
having to adjust %effort per task??
Andrew