Resource calendar

B

Bret

Is there anyway to get a calendar type of view for one
resource (or all resources) that would display their
tasks? So for example you could easily see that Joe is
working on task A from November 1 through the 3rd and then
task B from the 4th through the 6th. Any such report out
there?
 
D

Dale Howard [MVP]

Bret --

How about this:

1. Open the project in question
2. Click View - Calendar
3. Click Project - Filtered for - Using Resources
4. Select a resource and click OK

Let us know if this helps.
 
G

Guest

Almost. But what I would really like to see is all
projects assinged to a resource. If I open he Enterprise
Resources, I do not see anything in the calendar view. If
all the projects would show here, your response would work
perfectly. Any chance I'm missing a configuration
settting to get all the projects in one view? I am also
using Project server 2003.
 
D

Dale Howard [MVP]

Bret --

Why don't you create a master project consisting of the projects in which
you are interested, and then use the steps I detailed?
 
Top