Resource calendars

D

David

On an enterprise level if I have individual calendars set
for resources on a particular project & this resource has
assignments in other projects. Is it possible to limit his
calender to specific project only OR do I have to change
his calender in the Resource pool?
Regards,
David.
 
K

Kevin Flanagan

Two options come to mind:
1) You would have to change his calendar in the resource
pool OR
2) Create a task calendar for that resource's tasks in
the one project which would modify the work just in that
one project. You may need to check the box that says to
ignore the resource calendar unless the task calendar and
the resource calendar allow work to be at the same
avcailability as the resource calendar.

Kevin
 
Top