resource capacity

  • Thread starter Resource Capacity Planning question
  • Start date
R

Resource Capacity Planning question

I'm not using the EPM yet but I have an mpp which shows the work and I can
see the remaining availablity but I'd like to see a total of work and
availabity by resource group. Any ideas of how to get that ?
 
D

Dale Howard [MVP]

You might try the following:

1. Click View - Resource Usage
2. Click View - Table - Work
3. Click Project - Group by - Resource Group
4. Click the Show button on the Formatting toolbar and select Outline Level
1
5. Right-click in the timephased grid and select the Work and Remaining
Availability details
6. Zoom the timescale to the level of zoom you wish, such as months/weeks

The Work column in the table on the left will show you the total amount of
Work assigned to each group. The Work and Remaining Availability details
will show you these values timephased at the level of zoom you select. Hope
this helps.




"Resource Capacity Planning question" <Resource Capacity Planning
(e-mail address removed)> wrote in message
news:[email protected]...
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top