When I click on view availability for a certain person in a certain week, my
project name isn't showing up exactly as it was created in Project 2007.
Also, the planned hours for that week are too high. Are these two issues
related? How do I fix this?

Thanks,
 
M

Marc Soester [MVP]

Hi Barbara,

That sounds to me like this resource was actually assigned to antoher
project (maybe with a similar Project name). It would certainly explain why
the project name is different and why the planned work is different.
Why dont you check if this is in fact a different project.