We are using PWA 2003. In Resource Center after selecting a resource,
clicking the View Availability icon, and then selecting the Assignment Work
by Project view provides both a graph and details of scheduled work by
project for the selected resource. However, selecting the View resource
assignments link on the left side pane for the same resource does not show
all the project and task assignments that are visible in the Assignment Work
by Project view. (The All assignments option under Assignments displayed is
used.)
Can anyone advise how to duplicate the Assignment Work by Project view in
View resource assignments?
Thanks in advance for any help.
clicking the View Availability icon, and then selecting the Assignment Work
by Project view provides both a graph and details of scheduled work by
project for the selected resource. However, selecting the View resource
assignments link on the left side pane for the same resource does not show
all the project and task assignments that are visible in the Assignment Work
by Project view. (The All assignments option under Assignments displayed is
used.)
Can anyone advise how to duplicate the Assignment Work by Project view in
View resource assignments?