T
Troy
I've added Resource Cost1 to the Ent Global File.
I want to use Resource Cost1 to store a billable rate which is different than Std Rate. I want to do this on a per project basis. Eventually, i want a macro that copies all values in Resource Cost1 over onto Std Rate.
However, I can't store a value in that Resource Cost1 on a project that is loaded into PS2003.
I could store a value thru the Resource Global but this only gives me 1 rate across all projects. i need a field to store a rate/cost that is different for each project.
Is there any cost fields on the Resource Sheet that i can use to store a value for each and every project? Or how can i get the Resource Cost1 to work?
I want to use Resource Cost1 to store a billable rate which is different than Std Rate. I want to do this on a per project basis. Eventually, i want a macro that copies all values in Resource Cost1 over onto Std Rate.
However, I can't store a value in that Resource Cost1 on a project that is loaded into PS2003.
I could store a value thru the Resource Global but this only gives me 1 rate across all projects. i need a field to store a rate/cost that is different for each project.
Is there any cost fields on the Resource Sheet that i can use to store a value for each and every project? Or how can i get the Resource Cost1 to work?